Reconstruction of the exit road “Princat Topia”, Phase II

Status

Completed

Cost in Euro

764.969 €

Cost in Albanian Lek

95.009.201 lek

This project has been financed through the decision taken by the Committee for the Development of Regions March 16th 2015, under the local and regional infrastructure financing scheme.

Project Typeroads
MunicipalityKavaja
InvestorsMunicipality of Kavaja
Contractors
Construction CompanyG.P.G. Company
Supervisory companyUniversal Engineering 08